|
|
| |
|
Winter 2007 Platform Widening
Project
background
to this story | ||
![]() |
![]() | |
|
In January the platform
widening work was completed. The widened section is in the foreground of
the photo above. The fence length has also been reduced.
(Compare this photo to those below) Over the weekend of 9th & 10th February the track work rebuild was started. Photos above and top right shop the point in its new location and a team using portable electric tampers to pack ballast under the timbers (sleepers) to ensure alignment. The team in the foreground in top right and right photos are relaying sleepers to extend the loop to join the point. It is expected that another "track bash" weekend in early March will see the final track panel and all tamping completed. Part of the old locomotive water supply bracket foundations can just be seen in front the lad with the pale blue overalls in the top right photo. Much of this will probably have to be removed to provide the necessary clearences. |
![]() | |
|
Platform Widening - the project | ||
![]() |
Ever since the Bodmin & Wenford Railway commenced
running trains from Bodmin Parkway the longest train that it was possible
to "run round" was 4 coaches.
"Run round" means to take the locomotive off the front of the train and then to move past the train on the adjacent Loop line and then recouple to what was the back so that the train may proceed in the opposite direction. This meant that 2 locomotives were required to operate trains longer than 4 coaches and the train would be "top and tailed" with a loco at each end. The plan is to move the point
approximately 60 feet east towards Liskeard (away in the photo left)
extend the headshunt and then widen a short length of platform by up to
approximately 18 inches. | |
|
The point (below) moves towards the camera position. (Right) The headshunt is very near to the Up Main line and all work will be carried out by arrangement with Network Rail. It is anticipated that the work will be completed by March 2008 before the main operating season. Santa Special Trains will not run to or from Bodmin Parkway nor will those on December 26 & 31 or January 1. |
| |
![]() |
| |